Please find below the programmed dates for the works on the A34/M40 Junction 9 Wendlebury Improvement. The dates are the most current estimates of when the works will happen but are susceptible to changes as the works progress. The information given below relates to the traffic management arrangements during the day and night.
The Project concerns the slip-roads, the roundabout and side roads - not the main carriageway of the Motorway. The strategy is to maintain two lanes through the works during day time; narrowing to one lane and closures will take place at nights only.
The A34 southbound embankment is now widened and the additional third lane is being built. Two narrow running lanes (with steel barriers for road user and workforce safety) will remain for the safe completion of kerbing/ drainage/ paving works).
Works from late October until December include various night-time lane closures and junction closures to adjust kerb lines and to resurface the widened southbound A34 and around the gyratory. The renewed white lines will then provide M40 Oxford – bound traffic with an additional (third) full-width lane up the M40 southbound off-slip, around the gyratory and down the southbound A34 for a distance of 600 metres.
To avoid inconvenience to road users the planned new Traffic Light installation has been brought forward by including it in the current works – with completion before Christmas.
To better control the flow of traffic, and to provide a safer environment for road users and the workforce, a 40mph speed limit will be in place with a 10mph convoy system introduced for night work where required for safety.
Traffic Management arrangements for the coming week will be:
Please be advised that the following traffic management will be in place for the A34/M40 Junction 9 Improvement Scheme over the next two weeks:-
Tuesday 1 - Friday 4 March : There will be various overnightlane closures on the M40 J9 roundabout.
Saturday 5 March : There will be a full closure of the southbound exit slip-road at M40 J9 from 10pm on Saturday 5 March until 5am on Sunday 6 March. A clearly signed diversion via junction 8a will be in place.
Monday 7 - Friday 11 March : There will be various overnightlane closures on the M40 J9 roundabout.
These lane closures are to complete additional remedial works identifed during a rece inspection
For any more information please contact HAIL on 0300 123 5000 or visit the scheme web page at http://www.highways.gov.uk/roads/projects/3735.aspx