Please find below the programmed dates for the works on the A34/ M40 Junction 9 Wendlebury Improvement. The dates are the most current estimates of when the works will happen but are susceptible to changes as the works progress. The information given below relates to the traffic management arrangements during the day and night.
To better control the flow of traffic, and to provide a safer environment for road users and the workforce, a 40mph speed limit will be in place with a 10mph convoy system introduced for night work where required for safety..
Traffic Management arrangements for the coming week will be:
Start Date
Aug 9th 2010
End Date
Early Nov. 2010
Desc of Traffic Mgmt/Works Activity
Day
Night
Day - same as night
On the A34 southbound and the M40 northbound off-slip the two narrow-lanes configuration with temporary steel safety barrier (introduced over the weekend of Aug. 7th /8th 2010) will remain unchanged until early November.
The temporary 40mph speed limit will remain in force through the works.
This arrangement provides a safe layout for road users and for the workforce whilst continuing to provide two running lanes for traffic.
The works are due to be completed by January 2011.
For any more information please contact HAIL on 0300 123 5000 or visit the scheme web page at http://www.highways.gov.uk/roads/projects/3735.aspx